An 81,587 sq ft industrial refurbishment delivered through challenging autumn conditions, combining roofing and gutter works, electrical validation, ancillary upgrades, and external improvements while maintaining progress throughout.
Project Manager
Andy Jones
Operations ManagerAs Operations Manager, Andy oversees the day-to-day delivery of some of Zeno’s projects, coordinating trades, programme, and site logistics so complex refurbishments run smoothly and hand over on time.
Visit staff profile
Project Overview
Spring Road presented a challenging refurbishment programme, delivered across the autumn months with unpredictable weather creating additional complexity for the works.
Covering an 81,587 sq ft industrial unit, the project included extensive roofing and gutter works, electrical validation, ancillary upgrades, and minor external works. With a significant proportion of the programme taking place externally, careful planning and flexibility were essential to maintain progress while responding to changing site conditions.
Zeno Contracts coordinated the works with a focus on keeping the programme moving safely and efficiently, adapting sequencing where required without compromising the quality of the finished project.
The successful delivery of Spring Road demonstrates Zeno’s ability to manage complex industrial refurbishment projects and deliver against challenging programmes, even when external conditions are working against us.